Question: Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters

Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc.

• Activities H, R2, T1 start the project.

• Activity T2 can start when Activities H, E1 and S are completed.

• Activity E1 also depends on Activity R2.

• Activity X follows Activity H and precedes Activity L.

• Activity E is preceded by Activities T2 and P1.

• The predecessors to Activity G are Activities L, T2 and P1.

• The successors to Activity T1 are Activities E1, S, W and D2.

• Activity P1 cannot begin until Activity W is finished.

• Activity P2 and F follow Activities W and D2, and precede Activities E and R1.

• Activity O2 depends on T2 and P1 , and precedes Activity L.

Q2. (5 marks)

Compare and contrast the project evaluation and review technique (PERT) with the critical path method (CPM).

Q3. (5 marks)

Using the information in the table below, assuming that the project team will work a standard working week (5 working days in a week) and that all tasks will start as soon as possible:

Task

Description

Duration (Working days)

Predecessor/s

A

Requirement Analysis

5

B

Systems Design

15

A

C

Programming

25

B

D

telecoms

15

B

E

Hardware installation

30

B

F

Integration

10

C, D

G

System Testing

10

E, F

H

Training/Support

5

G

I

Handover and Go-Live

5

H

Determine the critical path of the project.

Calculate the planned duration of the project in weeks

Q4. (10 marks)

Explain in detail Eliyahu Goldratt’s Theory of Constraints with a brief note on its application in Project Management.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Q1 Construct an Activity on Arrow AOA Network Diagram Here is the constructed Activity on Arrow AOA network diagram based on the given activity dependencies Each activity is represented as a node and ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!