Question:
Transcribed Image Text:
A construction firm from the Phuket Province of Thailand has a five activity project lined up for the coming month. They have had some difficulty getting firm estimates on the activity durations and have resorted to the three time estimates approach to plan the project. The activities and optimistic, most likely, and pessimistic estimates (in days) for each are shown in the table. Activity A B C D E 18.83 14.83 16.67 Predecessor 0.8849 A 0,3849 - What is the expected completion time for the project? 19.00 0.9641 D Optimistic 5 11 8 9 6 Most Likely 7 15 12 11 8 Expected completion time of the project 23 days Variance of project completion time - 2.77 What is the probability of completing the project over 20 days? 0.0359 Question 2 (2 points) Jos used a project management software package and has determined the following results for a given project: Pessimistic 10 18 15 12 10 A construction firm from the Phuket Province of Thailand has a five activity project lined up for the coming month. They have had some difficulty getting firm estimates on the activity durations and have resorted to the three time estimates approach to plan the project. The activities and optimistic, most likely, and pessimistic estimates (in days) for each are shown in the table. Activity A B C D E 18.83 14.83 16.67 Predecessor 0.8849 A 0,3849 - What is the expected completion time for the project? 19.00 0.9641 D Optimistic 5 11 8 9 6 Most Likely 7 15 12 11 8 Expected completion time of the project 23 days Variance of project completion time - 2.77 What is the probability of completing the project over 20 days? 0.0359 Question 2 (2 points) Jos used a project management software package and has determined the following results for a given project: Pessimistic 10 18 15 12 10
Expert Answer:
Related Book For
Project Management in Practice
ISBN: 978-0470533017
4th edition
Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco
Posted Date:
Students also viewed these accounting questions
-
A manufacturing project has five independent phases whose completion must be sequential. The time to complete each phase is a random variable. The mean and standard deviation of the time for each...
-
In a construction company, project completion time is considered to be normally distributed with mean completion time being 16 weeks. There is an 80% probability that a project will take between 14...
-
A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the project completion time is normally distributed. (a) What is the probability of...
-
Use the following timeline to answer the question(s) below. 0 1 2 3 $600 $1200 $1800 At an annual interest rate of 7%, the future value of this timeline in year 3 is?
-
Describe how data can be sorted, and discuss several uses of sorting.
-
The body composed of slender rods of mass p per unit length is lying motionless on the smooth horizontal surface when a linear impluse P dt is applied as shown. Determine the velocity v B of corner B...
-
Show that another way of writing the flux due to pressure diffusion is in terms of partial molar volume and the total mixture density is \[J_{\mathrm{A}}^{*}(\text { pressure diffusion })=-C...
-
Large Land Photo Shop has asked you to determine whether the companys ability to pay current liabilities and total liabilities improved or deteriorated during 2015. To answer this question, you...
-
Windsor Advertising was founded in January 2013. Presented below are adjusted and unadjusted trial balances as of December 31, 2020. WINDSOR ADVERTISING TRIAL BALANCE DECEMBER 31, 2020 Unadjusted Dr....
-
How is Integration from Calculus and Calculus II used and applied in the field of Computer Sciences.
-
There are a huge number of individuals and firms who are out there selling their organizational development services. Take a look at videos and/or webpages of OD consultants and find a company or...
-
How can a college basketball coach use lean system strategies to improve the team's performance and win the national championship? What wastes can be eliminated from the team's training and...
-
GROUP DISCUSSION BEFORE CLASS STARTS : 1. WHAT IS CHANGE 2. WHY PEOPLE RESIST CHANGE 3. SOURCES OF RESISTANCE TO CHANGE 4. TACTICS FOR OVERCOMIMG RESISTANCE TO CHANGE.
-
CTs are used to measure the current flowing in a power system. They step down high currents to a level that can be safely measured by instruments. The reduced current is then proportional to the...
-
4) (2 Points] Consider the following closed queueing network in which job sizes are Exponentially distributed. The service rate for each server is p =3 and # = 1, respectively. The value of p denotes...
-
Mass MA = 30 kg and mass MB = 26 kg. They have velocities (in m/s) A = 12 i-25 j and VB -28 +14 + 14 j. Part A Determine the velocity of the center of mass of the system. Express your answer using...
-
As the leader of a problem-solving team, you are tasked with leading a high-performing team. During the process of leading and managing the team, you have noticed things that could improve, such as...
-
The financial statements of Eastern Platinum Limited (Eastplats) are presented in Appendix A at the end of this textbook. Instructions (a) Does East plats report any investments on its statement of...
-
When activity times are known with certainty, the critical path is defined as the set of activities on a path from the projects start event to its finish event that, if delayed, will delay the...
-
1. Estimate the final construction budget. 2. What should they do about the work slowdown? 3. Create a Gantt chart with the revisions to the duration of the interiors step. When will the project be...
-
A four - year financial project is forecast to have net cash inflows of $20,000; $25,000; $30,000; and $50,000 in the next four years. It will cost $75,000 to implement the project, payable at the...
-
Which of the following is not an important function of heterochromatin formation? a. Gene silencing b. Prevention of viral proliferation c. Splicing of pre-mRNA d. Prevention of movement of...
-
If the VIN3 gene had a loss-of-function mutation, how do you think that would affect the phenotypes of summer-annual and winter-annual Arabidopsis plants? a. Neither type would flower. b. Both types...
-
The effects of paramutation may vary with regard to a. the likelihood that the parmutagenic allele will alter the paramutable allele. b. the stability of the paramutagenic allele over the course of...
Study smarter with the SolutionInn App