Question: A construction firm is evaluating two value-adding projects. The first project deals with building access roads to a new terminal at the local airport. The

A construction firm is evaluating two value-adding projects. The first project deals with building access roads to a new terminal at the local airport. The second project is to build a parking garage on a piece of land that the firm owns adjacent to the airport.

The firm's decision will be to
A Accept both projects because they are independent projects
B Accept both projects because they are contingent projects
C Pick the one that adds the most value because they are mutually exclusive projects
D Pick neither project