Question: A construction project has the following parameters: AC = $25,000 BAC = $80,000 EV = $20,000 How much money is expected to be spent on

A construction project has the following parameters: AC = $25,000 BAC = $80,000 EV = $20,000 How much money is expected to be spent on the remainder of the project? Assume the trend will continue. O a. $100,000 O b. $75,000 O c. $80,000 O d. $55,000 A construction project has the following parameters: AC = $25,000 BAC = $80,000 EV = $20,000 How much money is expected to be spent on the remainder of the project? Assume the trend will continue. O a. $100,000 O b. $75,000 O c. $80,000 O d. $55,000