Question: A construction project has the following parameters: AC = $30,000 BAC = $80,000 EV = $20,000 How much money is expected to be spent on

A construction project has the following

A construction project has the following parameters: AC = $30,000 BAC = $80,000 EV = $20,000 How much money is expected to be spent on the remainder of the project? Assume the trend will continue. a. $100,000 b. $50,000 c. $90,000 O d. $120,000 X