Question: A construction project is broken down into the following 10 activities: Activity Immediate Pred Weeks A - 6 B A 3 C A 4 D
A construction project is broken down into the following 10 activities:
| Activity | Immediate Pred | Weeks |
| A | - | 6 |
| B | A | 3 |
| C | A | 4 |
| D | A | 2 |
| E | B, C | 4 |
| F | C | 3 |
| G | D | 7 |
| H | E | 3 |
| I | F, G | 5 |
| J | H, I | 7 |
- Please draw the network.
- What is the critical path?
- How many weeks will it take to complete the project?
- How much slack does each of the activities have?