Question: A construction project is falling behind schedule, and the project manager is contemplating crashing to expedite completion. What is the most likely potential drawback of

A construction project is falling behind schedule, and the project manager is contemplating crashing to expedite completion. What is the most likely potential drawback of crashing a project?
Group of answer choices
Crashing may compromise the quality of work
Crashing is only effective in projects with ample resources
Crashing has no impact on project costs
Crashing extends the project duration