Question: A contractor bids on a job installing sprinkler systems at 12 residential complexes. The contractor expects a 90% learning curve. He expects the first job

A contractor bids on a job installing sprinkler systems at 12 residential complexes. The contractor expects a 90% learning curve. He expects the first job to take 10 days. How many days should the contractor budget for?

a. The final four installation

b. The first four installations

c. The second four installations