Question: A contractor has six jobs awaiting processing at a workstation that is also a bottleneck and therefore is only capable of processing one job at
A contractor has six jobs awaiting processing at a workstation that is also a bottleneck and therefore is only capable of processing one job at a time. The day the job was received, its processing time and due date are given in the following table. It is now day 7.

Calculate the average throughput time and, for each job, the number of days overdue using the following priority sequencing rules:
i. First-come-first-serve
ii. Earliest due date
iii. Shortest processing time
Which rule should be used, in your opinion? Why?
Day Job Job was Received B 2 3 D 4 E 5 F 6 Job Processing Job Due Time (days) Day 6 29 8 15 5 37 2 25 9 32 4 43Step by Step Solution