Question: A CPI or SPI value less than one indicates that the project is Question 3 options: Over cost or ahead of schedule Under cost or

A CPI or SPI value less than one indicates that the project is
Question 3 options:
Over cost or ahead of schedule
Under cost or ahead of schedule
Under cost or behind schedule
Over cost or behind schedule