Question: A CPI or SPI value less than one indicates that the project is currently Multiple Choice under cost or behind schedule. over cost or ahead
A CPI or SPI value less than one indicates that the project is currently
Multiple Choice
under cost or behind schedule.
over cost or ahead of schedule.
under cost or ahead of schedule.
over cost or behind schedule.
on cost or on schedule.