Question: A CPl or SPl value less than one indicates that the project is currently (8 00:23:34) Multiple Cholce eBook References under cost or behind schedule.

A CPl or SPl value less than one indicates that the project is currently (8 00:23:34) Multiple Cholce eBook References under cost or behind schedule. under cost or ahead of schedule. over cost or ahead of schedule. on cost or on schedule. over cost or behind schedule