Question: a. Create a project schedule in MS Excel ensuring that it reflects the predecessor/successor relationships identified in the table. b. How long will it take
a. Create a project schedule in MS Excel ensuring that it reflects the predecessor/successor relationships identified in the table.
b. How long will it take to complete the project?
c. Joan and Alcides are not fully dedicated to the project. Joan is only available for 4 hours each day, and Alcides is available for 6 hours per day. The original estimated duration (in 8-hour days) results in over-allocation of Joan and Alcides. Prepare a resource-leveled project schedule in MS Excel. How long will it take to complete the project in a resource-leveled environment?
Using the data below
| Activity ID | Activity | Immediate Predecessor | Duration in days | Resource | Work Hours per Day |
| A | Evaluate freezers | 2 | Alcides | 6 | |
| B | Chart temperatures | 6 | Joan | 4 | |
| C | Review service record | 2 | Alcides | ||
| D | Consult with HVAC engineer | A, B, C | 3 | Alcides | |
| E | Develop construction plan | D | 10 | Joan | |
| F | Complete IC assignment | E | 2 | Alcides | |
| G | Complete ROI analysis | E | 5 | Joan | |
| H | Conduct regulatory review | E | 4 | Joan | |
| I | Obtain construction approval | F, G, H | 2 | Alcides |