Question: a Determine the expected time for each activity. b) Determine the variance and standard deviation for each activity. c) Using the critical path A->C-F--H-JK, determine
a Determine the expected time for each activity.
b) Determine the variance and standard deviation for each activity.
c) Using the critical path A->C-F--H-JK, determine the expected completion time for the proiect.
d] Determine the variance and standard deviation for the project.
e) What is the probability of completing the project in less than 40 weeks?
f) What is the probability of completion of project before week 36?

\begin{tabular}{ccccc} \hline & & \multicolumn{3}{c}{ Time Estimates (in weeks) } \\ \cline { 3 - 5 } & Immediate & \multicolumn{3}{c}{ Most } \\ Activity & Predecessor(s)A & Optimistic & Likely & Pessimistic \\ \hline A & - & 4 & 8 & 10 \\ B & A & 2 & 8 & 24 \\ C & A & 8 & 12 & 16 \\ D & A & 4 & 6 & 10 \\ E & B & 1 & 2 & 3 \\ F & E, C & 6 & 8 & 20 \\ G & E, C & 2 & 3 & 4 \\ H & F & 2 & 2 & 2 \\ I & F & 6 & 6 & 6 \\ J & D, G, H & 4 & 6 & 12 \\ K & I, J & 2 & 2 & 3 \\ \hline \end{tabular}