Question: A developer that specializes in compact urban amusement parks has formulated the following list of activities necessary to release a contract for the preparation of
A developer that specializes in compact urban amusement parks has formulated the following list of activities necessary to release a contract for the preparation of a new site. Times are given in weeks.
Estimated Immediate Activity Time
Activity Description Predecessors (weeks)
A Preliminary architectural design _ 14
B Community impact hearings A 2
C Line up potential financiers A 12
D Permit application A 5
E Negotiate comity impact details B 6
F Final Design B 8
G Loan approval C, F 3
H Permit hearings D 2
I Permit granting H 8
J Negotiate contract G, I 6
K Release contract E, J 3
Which activities are on the critical path