Question: A developer that specializes in compact urban amusement parks has formulated the following list of activities necessary to release a contract for the preparation of
A developer that specializes in compact urban amusement parks has formulated the following list of activities necessary to release a contract for the preparation of a new site. Times are given in weeks.
Estimated Immediate Activity Time
Activity Description Predecessors (weeks)
A Preliminary architectural design _ 12
B Community impact hearings A 6
C Line up potential financiers A 12
D Permit application A 5
E Negotiate comity impact details B 8
F Final Design B 6
G Loan approval C, F 5
H Permit hearings D 2
I Permit granting H 10
J Negotiate contract G, I 6
K Release contract E, J 3
A. Draw a project network. 7 points.
B. Develop a table showing the early start time, early finish time, late start time, late finish time, and slack time for each activity. 7 points.
C. What is the earliest time the project can be completed. 1 point.
D. Which activities are on the critical path. 1 point.