Question: a. Draw a network diagram using the activity-in-the-box format using the information provided below. Also show the ES, LS, EF, and LF times for each

a. Draw a network diagram using the
a. Draw a network diagram using the activity-in-the-box format using the information provided below. Also show the ES, LS, EF, and LF times for each activity on the diagram). Format count! Immediate Predecessor Slack Activity 1. 2. B 3. C 4. D 5. E 6. F 7 G 8. H Duration 3 S. 1 6 5 3 4 2 1 1 2,3 2 4 5,6 6,7 b. Give the slack time for each activity. Immediate Predecessor ES EF LS LF Slack Activity 1. 2. B 3. c 4. D 5. E 6. F 7. G 8 H Duration 3 5 1 6 5 3 4 2 1 1 23 2 4 5.6 6,7