Question: a . Draw a product structure tree ( tree diagram ) for the scissors. Lead times are 1 day for each component and final scissor
a Draw a product structure tree tree diagram for the scissors. Lead times are day for each component and final scissor assembly but days for the plastic grips. scissors are needed on Day On hand inventory: Straight blades bent blades and top blade assembly
Item
Scissors
Bottom Blade Assembly
Straight Blade
Straight Plastic Grip
Screw
Top Blade Assembly
Bent Blade
Bent Plastic Grip
b Material plans:
Master
Schedule for:
Scissors
Week
Beg. Inv.
Quantity
Scissors LT
Lot size: LotforLot
Beg. Inv.
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Plannedorder receipts
Plannedorder releases
Bottom Blade Assembly LT
Lot size: LotforLot
Beg. Inv.
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Plannedorder receipts
Plannedorder releases
Notes: Gross Requirements week PlannedOrder Releases of Scissors
Top Blade Assembly
LT
Lot size: LotforLot
Beg. Inv.
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Plannedorder receipts
Plannedorder releases
Notes: Gross Requirements week PlannedOrder Releases of Scissors
Screw LT
Lot size: LotforLot
Beg. Inv.
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Plannedorder receipts
Plannedorder releases
Notes: Gross Requirements week PlannedOrder Releases of Scissors
Straight Blade LT
Lot size: LotforLot
Beg. Inv.
Gross requirements
Scheduled receipts
o
Projected on hand
>
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock