Question: a. Draw a product structure tree (tree diagram) for the scissors. Lead times are 1 day for each component and final scissor assembly but 2
a. Draw a product structure tree (tree diagram) for the scissors. Lead times are 1 day for each component and final scissor assembly but 2 days for the plastic grips. 600 scissors are needed on
Day 6. On hand inventory: Straight blades = 200, bent blades - 350, and top blade assembly =
40.
b. Material plans: