Question: Given: a . Draw a product structure tree ( tree diagram ) for the scissors. Lead times are 1 day for each component and final

Given:
a. Draw a product structure tree (tree diagram) for the scissors. Lead times are 1 day for each component and final scissor assembly but 2 days for the plastic grips. 600 scissors are needed on Day 6. On hand inventory: Straight blades =200, bent blades =350, and top blade assembly =40.
b. Material plans:
 Given: a. Draw a product structure tree (tree diagram) for the