Question: a) Draw an activity on node network diagram b) What is the critical path? c) How long will it take you to finish the entire
a) Draw an activity on node network diagram
b) What is the critical path?
c) How long will it take you to finish the entire project?
Activity (A) activity time (3) days [Immediate Predecessor (M)
Activity (B) activity time (2) days [Immediate Predecessor (M)
Activity (C) activity time (1) days [Immediate Predecessor (B)
Activity (D) activity time (4) days [Immediate Predecessor (A)
Activity (E) activity time (7) days [Immediate Predecessor (F)
Activity (F) activity time (5) days [Immediate Predecessor (C)
Activity (G) activity time (2) days [Immediate Predecessor (C,D)
Activity (I) activity time (1) days [Immediate Predecessor (G,F)
Activity (J) activity time (4) days [Immediate Predecessor (I)
Activity (M) activity time (1) days [Immediate Predecessor (none)