Question: a) Draw an activity on node network diagram b) What is the critical path? c) How long will it take you to finish the entire

a) Draw an activity on node network diagram

b) What is the critical path?

c) How long will it take you to finish the entire project?

Activity (A) activity time (3) days [Immediate Predecessor (M)

Activity (B) activity time (2) days [Immediate Predecessor (M)

Activity (C) activity time (1) days [Immediate Predecessor (B)

Activity (D) activity time (4) days [Immediate Predecessor (A)

Activity (E) activity time (7) days [Immediate Predecessor (F)

Activity (F) activity time (5) days [Immediate Predecessor (C)

Activity (G) activity time (2) days [Immediate Predecessor (C,D)

Activity (I) activity time (1) days [Immediate Predecessor (G,F)

Activity (J) activity time (4) days [Immediate Predecessor (I)

Activity (M) activity time (1) days [Immediate Predecessor (none)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!