Question: a) Draw an AOA diagram representing the project below (3) b) Identify all the paths on the AOA diagram and calculate how long they are.
a) Draw an AOA diagram representing the project below (3)
b) Identify all the paths on the AOA diagram and calculate how long they are. (3)
c) What is the critical path for the project and how long is it? (1)
d) What is the shortest possible time it will take to complete this project? (1) e) identify 2 nodes acting as bursts (1) f) identify 2 nodes acting as merges (1) Draw on paper, take a picture or scan your drawing and upload it to this submission window. If you have problems, send it to me vial Blackboard e-mail.
Activity Start node Final node Duration A 1 2 2 B 1 3 1 C 1 4 3 D 2 5 3 E 3 5 3 F 4 6 3 G 3 6 3 H 4 7 7 I 6 8 4 J 5 8 3 K 7 8 4