Question: a ) Draw the AON network using the below information. b ) Determine the estimated duration and variance for all activities. c ) Compute ES

a) Draw the AON network using the below information.
b) Determine the estimated duration and variance for all activities.
c) Compute ES, EF, LS, and LF for all activities.
d) Determine the estimated total duration of the project and the critical path.
e) Draw a Gantt chart also.
FIRST TABLE IN THE PICTURE
f) Find the crashing cost per day.
SECOND TABLE IN THE PICTURE.
SOLVE FOR A,B,C,D,E,F WITH ALL STEPS
 a) Draw the AON network using the below information. b) Determine

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock