Question: FOR TABLE 1 a ) Draw the AON network using the below information. b ) Determine the estimated duration and variance for all activities. c

FOR TABLE 1
a) Draw the AON network using the below information.
b) Determine the estimated duration and variance for all activities.
c) Compute ES, EF, LS, and LF for all activities.
d) Determine the estimated total duration of the project and the critical path.
e) Draw a Gantt chart also.
FOR TABLE 2
f) Find the crashing cost per day. ANSWER A,B,C,D,E,F WITH STEPS PLZ.
 FOR TABLE 1 a) Draw the AON network using the below

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!