Question: a. Draw the network diagram for the information given in the table. Include es, ef, lf, and ls. b. Find and label each path for

a. Draw the network diagram for the information given in the table. Include es, ef, lf, and ls.

b. Find and label each path for the network diagram on the page of the network diagram

c. Find the total float for each path and put it beside the path. (IE Path ABCD = TS 4 where TS is the total slack or total float for path ABCD)

d. Find the critical path(s) for the network diagram. Remember: It will have a TS of 0

 a. Draw the network diagram for the information given in thetable. Include es, ef, lf, and ls. b. Find and label each

Critical Path: \begin{tabular}{|l|c|c|c|} \hline \multicolumn{4}{|c|}{ Activity 3 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & O & - & \\ \hline A & 6 & Start & \\ \hline B & 2 & A & \\ \hline C & 4 & Start & \\ \hline D & 3 & B, C & \\ \hline E & S & C & \\ \hline F & 7 & E & \\ \hline G & 6 & D & \\ \hline H & 9 & G,F & \\ \hline End & 0 & H & \\ \hline \end{tabular} Critical Path: \begin{tabular}{|l|c|c|l|} \hline \multicolumn{5}{|c|}{ Activity 4 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 2 & Start & \\ \hline B & S & A & \\ \hline C & 4 & A & \\ \hline D & 1 & B & \\ \hline E & 3 & C & \\ \hline F & 2 & D, E & \\ \hline G & 3 & Start & \\ \hline H & 3 & G & \\ \hline L & 1 & H & \\ \hline End & 0 & F, I & \\ \hline \end{tabular} Critical Path: \begin{tabular}{|c|c|c|c|} \hline \multicolumn{4}{|c|}{ Activity 5} \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 3 & Start & \\ \hlineB & 5 & Start & \\ \hline C & 1 & A & \\ \hline D. & 2 & B & \\ \hline E & 6 & C. D & \\ \hline F & 3 & C & \\ \hline G. & 4 & E & \\ \hline H & 5 & F,G & \\ \hline End & 0 & H & \\ \hline \end{tabular} \begin{tabular}{|l|c|c|l|} \hline \multicolumn{5}{|c|}{ Activity 6 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 4 & Start & \\ \hline B & 2 & A & \\ \hline C & 5 & A & \\ \hline D & 3 & B & \\ \hline E & 4 & C & \\ \hline F & 7 & C & \\ \hline G & 8 & E, F & \\ \hline H & 10 & D, G & \\ \hline End & 0 & H & \\ \hline B & & & \\ \hline \end{tabular} \begin{tabular}{|l|c|c|l|} \hline \multicolumn{4}{|c|}{ Activity 1 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 2 & Start & \\ \hline B & 5 & Start & \\ \hline C & 6 & Start & \\ \hline D & 1 & Start & \\ \hline E & 6 & A & \\ \hline F & 2 & B & \\ \hline G & 3 & C & \\ \hline H & 7 & D & \\ \hline N & 1 & E & \\ \hline I & 9 & F & \\ \hline K & 5 & G & \\ \hline L & 4 & H & \\ \hline M & 3 & I, J, K, L & \\ \hline End & 0 & M & \\ \hline Crical Path & & & \\ \hline \end{tabular} \begin{tabular}{|l|c|c|l|} \hline \multicolumn{4}{|c|}{ Activity 2 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 9 & Start & \\ \hline B & 7 & Start & \\ \hline C & 5 & Start & \\ \hline D & 7 & A & \\ \hline E & 5 & B & \\ \hline F & 1 & C & \\ \hline G & 3 & D & \\ \hline H & 4 & E & \\ \hline I & 2 & F & \\ \hline K & 4 & G, H & \\ \hline L & 6 & I & \\ \hline M & 2 & K, L & \\ \hline End & 0 & M & \\ \hline Critical Path: & & & \\ \hline \end{tabular} \begin{tabular}{|l|l|l|l|} \hline \multicolumn{3}{|c|}{ Activity 3} \\ \hline Activity & Duration & Dependency & Fioat \\ \hline Start & & \end{tabular} \begin{tabular}{|l|l|l|l|} \hline \multicolumn{3}{|c|}{ Activity 4} \\ \hline Activity & Duration & Dependency & Float \\ \hline \end{tabular} Critical Path: \begin{tabular}{|l|c|c|c|} \hline \multicolumn{4}{|c|}{ Activity 3 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & O & - & \\ \hline A & 6 & Start & \\ \hline B & 2 & A & \\ \hline C & 4 & Start & \\ \hline D & 3 & B, C & \\ \hline E & S & C & \\ \hline F & 7 & E & \\ \hline G & 6 & D & \\ \hline H & 9 & G,F & \\ \hline End & 0 & H & \\ \hline \end{tabular} Critical Path: \begin{tabular}{|l|c|c|l|} \hline \multicolumn{5}{|c|}{ Activity 4 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 2 & Start & \\ \hline B & S & A & \\ \hline C & 4 & A & \\ \hline D & 1 & B & \\ \hline E & 3 & C & \\ \hline F & 2 & D, E & \\ \hline G & 3 & Start & \\ \hline H & 3 & G & \\ \hline L & 1 & H & \\ \hline End & 0 & F, I & \\ \hline \end{tabular} Critical Path: \begin{tabular}{|c|c|c|c|} \hline \multicolumn{4}{|c|}{ Activity 5} \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 3 & Start & \\ \hlineB & 5 & Start & \\ \hline C & 1 & A & \\ \hline D. & 2 & B & \\ \hline E & 6 & C. D & \\ \hline F & 3 & C & \\ \hline G. & 4 & E & \\ \hline H & 5 & F,G & \\ \hline End & 0 & H & \\ \hline \end{tabular} \begin{tabular}{|l|c|c|l|} \hline \multicolumn{5}{|c|}{ Activity 6 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 4 & Start & \\ \hline B & 2 & A & \\ \hline C & 5 & A & \\ \hline D & 3 & B & \\ \hline E & 4 & C & \\ \hline F & 7 & C & \\ \hline G & 8 & E, F & \\ \hline H & 10 & D, G & \\ \hline End & 0 & H & \\ \hline B & & & \\ \hline \end{tabular} \begin{tabular}{|l|c|c|l|} \hline \multicolumn{4}{|c|}{ Activity 1 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 2 & Start & \\ \hline B & 5 & Start & \\ \hline C & 6 & Start & \\ \hline D & 1 & Start & \\ \hline E & 6 & A & \\ \hline F & 2 & B & \\ \hline G & 3 & C & \\ \hline H & 7 & D & \\ \hline N & 1 & E & \\ \hline I & 9 & F & \\ \hline K & 5 & G & \\ \hline L & 4 & H & \\ \hline M & 3 & I, J, K, L & \\ \hline End & 0 & M & \\ \hline Crical Path & & & \\ \hline \end{tabular} \begin{tabular}{|l|c|c|l|} \hline \multicolumn{4}{|c|}{ Activity 2 } \\ \hline Activity & Duration & Dependency & Float \\ \hline Start & 0 & - & \\ \hline A & 9 & Start & \\ \hline B & 7 & Start & \\ \hline C & 5 & Start & \\ \hline D & 7 & A & \\ \hline E & 5 & B & \\ \hline F & 1 & C & \\ \hline G & 3 & D & \\ \hline H & 4 & E & \\ \hline I & 2 & F & \\ \hline K & 4 & G, H & \\ \hline L & 6 & I & \\ \hline M & 2 & K, L & \\ \hline End & 0 & M & \\ \hline Critical Path: & & & \\ \hline \end{tabular} \begin{tabular}{|l|l|l|l|} \hline \multicolumn{3}{|c|}{ Activity 3} \\ \hline Activity & Duration & Dependency & Fioat \\ \hline Start & & \end{tabular} \begin{tabular}{|l|l|l|l|} \hline \multicolumn{3}{|c|}{ Activity 4} \\ \hline Activity & Duration & Dependency & Float \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!