Question: (a) Draw the project network and determine the critical path(s) using AOA method and determine the critical path. (b)Draw project network from (a) using AON

(a) Draw the project network and determine the critical path(s) using AOA method and determine the critical path.
(b)Draw project network from (a) using AON method, filling the ES, EF, LS, LF and slack for each node.
Problem 1 Consider the following tasks for a project. Task Time (days) Immediate predecessors A B D E F G H I J WNION uw 3 2 6 2 3 3 5 1 1.5 2 A A A B F,HStep by Step Solution