Question: a. Draw the project network and solve it to determine ES,EF,LS, and LF. b. Identify the critical path, and specify project completion time. Activity Predecessor

a. Draw the project network and solve it to determine ES,EF,LS, and LF.

b. Identify the critical path, and specify project completion time.

Activity Predecessor Time(weeks)

A -- 6

B -- 8

C A,B 4

D B 9

E C,D 11

F E 3

G D,E 5