Question: a. Draw the Project Network diagram b. Calculate the ES, EF, LS, LF, and Slack for each activity. C. What is Critical Path and project

a. Draw the Project Network diagram b. Calculate

a. Draw the Project Network diagram b. Calculate the ES, EF, LS, LF, and Slack for each activity. C. What is Critical Path and project completion time? Present your answer in table format, ie. Activity A ES EF LS LF Slack Activity B ES etc ... Activity Precedent Activity Duration A None 6 B None 4 A 3 A&B 5 E D 8 F 9 M 0 G E&F 4