Question: Use the table shown below: a. Draw the Project Network diagram b. Calculate the ES, EF, LS, LF, and Slack for each activity. C. What
Use the table shown below:
a. Draw the Project Network diagram
b. Calculate the ES, EF, LS, LF, and Slack for each activity.
C. What is Critical Path and project completion time?
Present your answer in table format, ie.
Activity A ES EF LS LF Slack
Activity B ES etc ...
| Activity | Precedent Activity | Duration |
| A | None | 6 |
| B | None | 4 |
| C | A | 3 |
| D | A & B | 5 |
| E | D | 8 |
| F | C | 9 |
| G | E & F | 4 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts