Question: a. Draw the project network diagram for this project and identify those activities with slack number? (10%) b. What is the minimum time duration of
a. Draw the project network diagram for this project and identify those activities with slack number? (10%)
b. What is the minimum time duration of the project? (5%)
c. What is the critical path of the project? (5%)
d. How much will be the most economical way to complete the project in 33 weeks? (10%) 31 weeks?(10%)
1. The time for each activity to complete, the possible weeks by which that time can be reduced and the cost per week to decrease the activity time. The cost to complete the project in normal time is $12,000(40%) a. Draw the project network diagram for this project and identify those activities with slack number? (10\%) b. What is the minimum time duration of the project? (5\%) c. What is the critical path of the project? (5%) d. How much will be the most economical way to complete the project in 33 weeks? (10\%) 31 weeks?(10\%)Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock