Question: a) During a project, earned value analysis is performed, resulting in the following numbers: EV: 623,000; PV: 723,000; AC: 743,000. Which is correct? a. CV:
a) During a project, earned value analysis is performed, resulting in the following numbers: EV: 623,000; PV: 723,000; AC: 743,000.
Which is correct?
a. CV: +100,000; SV: +120,000
b. CV: -100,000; SV: -120,000
c. CV: -120,000; SV: -100,000
d. CV: +120,000; SV: +100,000
Explain the CV and SV:
a. The project is under budget and ahead of schedule
b. The project is above budget and behind schedule
c. The project is above budget and ahead of schedule
d. The project is under budget and behind schedule
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
