Question: A facility is trying to set up an assembly line, and has identified the various tasks, and their relationship to each other, as shown in

A facility is trying to set up an assembly line,
A facility is trying to set up an assembly line,
A facility is trying to set up an assembly line, and has identified the various tasks, and their relationship to each other, as shown in the following table. Managers wish to produce 600 units per day, working two 8-hour shifts. TASK PRECEDING TASK TIME TO PERFORM (SEC) A 20 B 30 25 10 D E 55 F D,B,C 30 G E H 25 40 F G a. What is the cycle time? 96 seconds seconds b. What is the theoretical minimum number of workstations? 3 c. By balancing the line based on longest processing time, what are the actual number of stations? Select) d. Is there an improved cycle time? yes e. Based on your answer to d., what is the efficiency? 82.2% f. Based on your answer to d., what is the idle time? Select] seconds 8. Based on your answer to d., what is the total actual idle time at all workstations over the course of f. Based on your answer to d, what is the idle time? [Select) seconds 8. Based on your answer to d., what is the total actual idle time at all workstations over the course of the two 8 hour shifts? Select]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!