Question: A final assembly ( A ) requires one week to assemble and has a component part ( B ) requiring two weeks to fabricate. Three
A final assembly A requires one week to assemble and has a component part B requiring two
weeks to fabricate. Three units of final assembly A and four units of part B are currently on hand.
The gross requirements for assembly A for the next weeks are as follows one part B is used on
each A:
a What are the planned order releases for part B using lotforlot lot sizing for both parts A and B
b What are the planned order releases for part using POQ for both parts A and
The resource profile for the frame is as follows:
tableItemWork Center,Setup Hours,Run HoursUnitLead TimeFrame weeksPart A weekPart B weekPart C weeksPart D week
Determine the capacity requirements for all work centers, assuming all usages are one, and that a new setup is required each week at each work center.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock