Question: Final assembly (X) requires one week to assemble and has a component part (A) requiring two weeks to be fabricated. Three units of final assembly
.png)
a. What are the planned order releases for part A using lot-for-lot sizing for both parts X and B?
b. What are the planned order releases for part A using POQ = 2 for both parts X and A?
WEEK 4 1 234 5 678 9 10 Assembly (A)4280623
Step by Step Solution
3.40 Rating (153 Votes )
There are 3 Steps involved in it
Corrections There are 3 units of final assemblyX and 4 units of part A The schedule above is for fin... View full answer