Question: Final assembly (X) requires one week to assemble and has a component part (A) requiring two weeks to be fabricated. Three units of final assembly

Final assembly (X) requires one week to assemble and has a component part (A) requiring two weeks to be fabricated. Three units of final assembly A and four units of part B are currently on hand. The gross requirements for assembly A for the 10 weeks are as follows (two of part A are used on each X):
Final assembly (X) requires one week to assemble and has

a. What are the planned order releases for part A using lot-for-lot sizing for both parts X and B?
b. What are the planned order releases for part A using POQ = 2 for both parts X and A?

WEEK 4 1 234 5 678 9 10 Assembly (A)4280623

Step by Step Solution

3.40 Rating (153 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Corrections There are 3 units of final assemblyX and 4 units of part A The schedule above is for fin... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

852-B-M-L-S-C-M (4448).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!