Question: 2. A final assembly (A) requires one week to assemble and has a component part (B) requiring two weeks to fabricate. Three units of final

 2. A final assembly (A) requires one week to assemble and

2. A final assembly (A) requires one week to assemble and has a component part (B) requiring two weeks to fabricate. Three units of final assembly A and four units of part B are currently on hand. The gross requirements for assembly A for the next 10 weeks are as follows (one part B is used on each A): a. What are the planned order releases for part B using lot-for-lot lot sizing for both parts A and B? b. What are the planned order releases for part B using POQ=2 for both parts A and B