Question: A foreman has determined processing times at a work center for a set of jobs with the due date given for each of them as

A foreman has determined processing times at a work center for a set of jobs with the due date given for each of them as follows. Process Time Due A 5 15 E! 1 9 C 6.5 1? D 4.5 13 E 3 8 What is the average job lateness Using the Earliest Due Date rule? O 1.9 O 2.5 O 1.? O 0.6 O 2.1