Question: A foreman has determined processing times at a work center for a set of jobs with the due date given for each of them as

A foreman has determined processing times at a work center for a set of jobs with the due date given for each of them as follows.
Process Time Due
A 59
B 110
C 6.511
D 4.514
E 38
What is the sequence Using the Earliest Due Date rule?
Cevap seenekleri grubu
E,B,C,A,D
B,E,A,C,D
E,A,B,C,D
E,B,D,A,C
B,E,A,D,C