Question: A foreman has determined processing times at a work center for a set of jobs with the due date given for each of them as

A foreman has determined processing times at a work center for a set of jobs with the due date given for each of them as follows.
Process Time Due
A 59
B 17
C 6.513
D 4.514
E 38
What is the average job lateness Using the Earliest Due Date rule?
Cevap seenekleri grubu
2.1
1.9
2.5
0.6
1.7

Step by Step Solution