Question: A foreman has determined processing times at a work center for a set of jobs with the due date given for each of them
A foreman has determined processing times at a work center for a set of jobs with the due date given for each of them as follows. A B C D E What is the average job lateness Using the Earliest Due Date rule? Process Time 5 1 6.5 4.5 3 Due 15 9 17 13 8
Step by Step Solution
There are 3 Steps involved in it
Answer From the given problem we get the below schedule data Job Processing time days Due Date days Critical Ratio a 45 10 222 b 6 17 283 c 52 12 231 d 16 27 1688 e 28 18 643 f 33 19 576 Formulas Crit... View full answer