Question: A foreman has determined the expected processing times at a machine for a set of jobs and now wants to sequence them. Given the information

A foreman has determined the expected processing times at a machine for a set of jobs and now wants to sequence them. Given the information shown below, do the following:
a. Determine the processing sequence using (1) MST,(2) SPT, (3) EDD, and (4)CR- For each sequence, calculate the average days late, the average flow time, and the average WIP.
b. Which rule is best?
A foreman has determined the expected processing times at a

Job Job Time (days) 4.5 6.0 5.2 1.6 2.0 3.3 Due Dato (days) 10 17 12 27 10 19 CI

Step by Step Solution

3.50 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Job Job Time Days Due Date Slack Critical Ratio a 45 10 10 45 55 10 45 222 b 60 17 17 6 11 17 6... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

686-B-M-L-O-M (5252).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!