Question: A four - step process has processing times of 3 , 4 , 7 , and 4 minutes for the four steps ( listed from

A four-step process has processing
times of 3,4,7, and 4 minutes for
the four steps (listed from start to
finish). After the third step, 37% of
items require rework, which entails
starting over again at step 1. All
items that are reworked are
successfully processed. Demand is
10 units per hour.
How many units per hour will the
second step process?
Note: Round your answer to 2
decimal places.