Question: Additional Algo 5-10 Rework A four-step process has processing times of 3, 7, 5. ond 6 minutes for the four steps listed from start to

Additional Algo 5-10 Rework A four-step process
Additional Algo 5-10 Rework A four-step process has processing times of 3, 7, 5. ond 6 minutes for the four steps listed from start to finish). After the third step, 32% of rems require rework, which entails storting over again or step 1. All items that are reworked are successfully processed. Demand is 10 units per hour Instruction: Round your answer to 2 decimal places How many units per hour will the second step process? units per hour