Question: A four-step process has processing times of 3, 4, 7, and 4 minutes for the four steps (listed from start to finish). After the third

A four-step process has processing times of 3, 4, 7, and 4 minutes for the four steps (listed from start to finish). After the third step, 37% of items require rework, which entails starting over again at step 1. All items that are reworked are successfully processed. Demand is 10 units per hour.

How many units per hour will the second step process?

Note: Round your answer to 2 decimal places.