Question: a) Full sequence questions: Scheduling Order 1 -> Job ____ Scheduling Order 2 -> Job ____ Scheduling Order 3 -> Job ____ Scheduling Order 4

a) Full sequence questions:
Scheduling Order 1 -> Job ____
Scheduling Order 2 -> Job ____
Scheduling Order 3 -> Job ____
Scheduling Order 4 -> Job ____
Scheduling Order 5 -> Job ____
Scheduling Order 6 -> Job ____
b) For the schedule developed using Johnsons rule, the total length of time taken to complete the six jobs (including the second operation): ___ Hours
Using Johnson's rule for 2-machine scheduling, the sequence is: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Scheduled Order Job Operation 1 (hours) 4 Operation 2 (hours) 8 Job B c 10 3 D 14 6 5 11 14 1 12 FStep by Step Solution