Question: A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time is 34 weeks, and
A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time is 34 weeks, and the project variance is 7 weeks. If the project deadline is set to be 51 weeks, then what is the probability that the project would need more than the given deadline to complete?
Input should be either 1 or 2, with 1 represents "more than 50%" and 2 represents "equal or less than 50%".
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock