Question: D Question 2 1 pts A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish

D Question 2 1 pts A future project has an
D Question 2 1 pts A future project has an uncertain finish time and the finish time follows a normal distribution. The project's expected finish time is 21 weeks, and the project variance is 9 weeks. If the project deadline is set to be 27 weeks, then what is the probability that the project would need more than the given deadline to complete? Input should be either 1 or 2 with 1 represents "more than 50%" and 2 represents "equal or less than 50% 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!