Question: Given the project within the table below calculate a. The critical path b. The minimum project duration c. The amount of slack for each activity
- Given the project within the table below calculate
a. The critical path
b. The minimum project duration
c. The amount of slack for each activity
Activity | Duration (hours) | Immediate Predecessors |
A | 4 | None |
B | 3 | None |
C | 10 | None |
D | 7 | B,C |
E | 1 | D |
F | 1 | E |
G | 5 | A,F |