Question: a ) Given in the following table are the task necessary for the assembly of Fine Cedar Chest, the length of the time needed to
a Given in the following table are the task necessary for the assembly of Fine Cedar Chest, the length of the time needed to perform each task, and the operations that must be completed prior to subsequent operations.
Work Element Precedence Time min
A None
B A
C B
D None
E D
F None
G F
H C E G
i Calculate the cycle time needed to compete cedar chests in a hour week
ii Determine the minimum number of workstations that can be use on the assembly line and still reach the production quota?
iii Balance the line and calculate the line efficiency
iv Rebalance the line with a cycle time of minutes. Determine the new minimum number of workstations output and line efficiency.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock