Question: a) Given the table of Software Developing Project below, what is the total normal cost of the project? ID Slope Normal Time Normal Cost, $
a) Given the table of Software Developing Project below, what is the total normal cost of the project?
| ID | Slope | Normal Time | Normal Cost, $ | Crash Time | Crash Cost, $ |
|---|---|---|---|---|---|
| A | 25 | 8 | 150 | 6 | 200 |
| B | 150 | 4 | 200 | 3 | 350 |
| C | 50 | 8 | 200 | 7 | 250 |
| D | 100 | 7 | 350 | 4 | 650 |
| E | 75 | 9 | 250 | 7 | 400 |
| F | 150 | 7 | 500 | 6 | 650 |
| G | 200 | 4 | 400 | 3 | 600 |
| H | 50 | 8 | 400 | 6 | 500 |
| I | 125 | 7 | 200 | 5 | 450 |
b) If the critical path is B-D-E-H-I, which activity should be crashed first?
Activity A, Activity B, Activity C, Activity D, Activity E, Activity F, Activity G, Activity H, or Activity I?
c) if you were asked to reduce the project by three days, what activities would you crash?
* Iteration 1: Activity ____.
* Iteration 2: Activity ____.
* Iteration 3: Activity ____.
d) What is the extra amount you will have to pay for crashing the project by three days?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts