Question: Given the above table of Software Developing Project, calculate the following: Slope? Maximum crash time? Provide your answers in the table below. Activity ID Slope

Given the above table of Software Developing Project, calculate the following:
Slope?
Maximum crash time?
Provide your answers in the table below.
Activity
ID Slope Max crash time Normal Time Normal Cost
Crash Time Crash Cost
A
8 $4,0006 $ 4,500
B
5 $5,5002 $ 7,000
C
10 $6,1007 $ 7,900
D
12 $4,7009 $ 5,000
E
6 $2,0504 $ 2,300
F
8 $1,2006 $ 1,700
G
5 $7,2004 $ 7,400
H
9 $7,5007 $ 8,000
I
2 $1,7502 $ 1,750
Answer text
Font sizeFont family
Activity
ID Slope Max crash time Normal Time Normal Cost
Crash Time Crash Cost
A
8 $4,0006 $ 4,500
B
5 $5,5002 $ 7,000
C
10 $6,1007 $ 7,900
D
12 $4,7009 $ 5,000
E
6 $2,0504 $ 2,300
F
8 $1,2006 $ 1,700
G
5 $7,2004 $ 7,400
H
9 $7,5007 $ 8,000
I
2 $1,7502 $ 1,750

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!